Decatur Street sidewalk improvement update: July 24, 2017

Decatur St. Sidewalk Update: July 7, 2017
July 7, 2017
Deals Along Bourbon Street During Construction
July 25, 2017

The City of New Orleans’ construction contractor, Hard Rock Construction, continues installing sidewalks along Decatur St. The overall project is approximately 53% completed and is anticipated to be completed by September 2017, weather permitting.

The scope of work includes:

  • Removing and replacing sidewalks along the 800 – 1300 blocks of Decatur St.
  • Installing Americans with Disabilities Act-compliant curb ramps.
  • Installing access ramps for impacted storefronts / residents during construction.
  • Temporary disruptions to access of storefronts for approximately one hour during concrete pours and brick installation.
  • Temporary lane shift.
  • No street parking during work hours.

 800 block of Decatur St.

  • (lake side)  –Work is scheduled to tentatively begin the week of July 31, 2017.
  • (river side)  – No work is scheduled to occur.

 900 block of Decatur St.

  • (lake side)  –Work is scheduled to tentatively begin the week of July 31, 2017.
  • (river side)  – No work is scheduled to occur.

 1000 block of Decatur St.

  • (lake side)  –Work is scheduled to be substantially complete on Friday, July 28, weather permitting. Delays have occur on this block due to weather and unexpected underground utility work.
  • (river side)  – No work is scheduled to occur.

 1100 block of Decatur St.

  • (lake side) –All work is substantially complete.
  • (river side) –  Crews began demolition work on the sidewalk last week. This week, crews will continue demolition work, establishing sidewalk forms and pour a new concrete base. All work is anticipated to be completed by the week of August 7, 2017.

 1200 block of Decatur St.

  • (lake side) –Work is scheduled to be substantially complete this week, pending weather conditions.
  • (river side) –  Start date TBD.

 1300 block of Decatur St.

  • (lake side) –All work is substantially completed.
  • (river side)  –All work is substantially completed.

For questions or concerns contact RoadworkNOLA at 504.658.ROAD (7623) or roadwork@nola.gov.

Comments are closed.