Entergy Infrastructure Improvement Project (500-800 Bourbon Street) Status Update: Friday, June 1, 2018

Community Meetings

The next bi-weekly community meeting will be held on Thursday June 7th at 10 a.m. on the corner of Bourbon and St Louis. NOTE: In the event of rain, we will meet at the Bourbon Orleans.

Traffic Status

Toulouse Street

The corner of Toulouse and Bourbon streets has remained open. Crews are performing work in the parking lanes on Toulouse. The work is expected to be completed on June 7, 2018. Entergy will work with businesses to facilitate deliveries, trash pickup and access to parking garages.

St. Ann

  • Gas line installation work started Tuesday, May 29, 2018.
  • Parking lane closures are occurring along St. Ann from Bourbon in order to allow for traffic to flow.
  • Expected duration of work in this block is approximately 3 to 4 weeks.
  • There are currently no expected road closures needed for this block.

500 Block of Bourbon

  • Work at St. Louis/Bourbon intersection is complete.
  • The St. Louis and Bourbon Street intersection is open to traffic.
  • Entergy work will resume in this block in approximately three weeks which is the week of June 10th.

600 Block of Bourbon

  • Crews began working in this area 5/23/18.
  • Parking lanes are closed in order to allow crews to work safely within water barricades.
  • Expected duration of work on this block is eight weeks.
  • Parking lanes will be unavailable while work is being done to underground facilities in the 600 block of Bourbon Street as outlined below.
  • Water barricades from Toulouse towards St. Peter were established on the river side on May 25th.
  • Parking lanes on the 600 block of Bourbon will be closed on the lake side in order to allow traffic flow to flow on the lake side.
  • Entergy personnel will work with delivery drivers who need to make deliveries, trash pickup and access to parking garages.
  • A few gas customers in the 500-600 blocks of Bourbon will receive a visit from Entergy personnel to obtain signatures for the gas improvements at their specific service locations.
  • There are currently no expected road closures needed for this block.

If you have any questions or concerns, please email agreen@entergy.com or call 504-670-3624.