The City of New Orleans, Department of Public Works and Sewerage & Water Board began a full reconstruction project on Bourbon Street from St. Louis to Dumaine streets (500-800 blocks) on September 17, 2018. Work is occurring sequentially from the 500 – 800 blocks, with ONLY one block fenced off at a time throughout construction. All businesses along this corridor are open and accessible throughout construction.
The City is roughly eighty five percent complete with the project; the contractor has fully reconstructed the roadway between St. Louis and St. Ann streets (500-750 blocks) with upsized drainage, a better sewer system, new sidewalks and new, smoother pavement. Additionally, the lighting and security have been upgraded between St. Louis and St. Peter streets. Entergy Gas and Entergy Electric have also completed upgrades in those blocks.
The $9.5 million cost-shared project, which is anticipated to run through fall 2019, was designed by Mott McDonald, LLC and is being constructed by Hard Rock Construction, LLC. Project partners include Entergy Electric, Entergy Gas, Cox Communications and AT&T.
Demobilization
for Southern Decadence
Like the demobilization for Mardi Gras, the
contractor has completely demobilized all labor and materials, including
fencing, from the site. The contractor will resume operations on Tuesday,
September 3. Entergy Gas and Entergy Electric have also demobilized from
their facility upgrades on St. Ann; crews will return on Tuesday as well.
Attend “Conversation
on the Corner”
The next Phase 2 bi-weekly community status
meeting will take place on Tuesday, September 10, at 10:30 a.m. at
the Bourbon Orleans Hotel, 717 Orleans Street, St. Joseph Salon.
Bollard Installation
Installation of the moveable bollard system that will enhance public safety in the 500-750 blocks of Bourbon Street will begin in the September timeframe. For more information on the Matador Bollard System, click here.
500 Block (St. Louis to Toulouse)
All major construction, with the exception of the bollard installation, has been completed on this block.
600 Block
(Toulouse to St. Peter)
All major construction, with the exception of the bollard installation, has
been completed on this block.
700 Block (St. Peter to Orleans)
All major construction, with the exception of the bollard installation, has been completed on this block.
Roadway Closure – 750 Block (Orleans to St. Ann)
All major construction, with the exception of the bollard installation, has been completed on this block. NOTE: There will be a future conduit installation on the riverside sidewalk that calls for removing an approximately 10 foot section of slate from the riverside sidewalk after the Southern Decadence demobilization.
Roadway
Closure – 800 Block (St. Ann to Dumaine)
Crews have completed installing new utilities and
poured the new concrete roadway (pictured). The roadway is currently open
to vehicular and pedestrian traffic. Work will resume in the 800 block on
Tuesday with reconstruction of the sidewalks. All businesses and
residences will have access ramps while the sidewalks are being constructed.
NOTE: The roadway will be closed to vehicular traffic while the
sidewalks are being constructed; this activity should take approximately three
weeks to complete.
Dumaine Intersection and Partial 900 Block Closure
Crews have completed upgrading the utilities and reopened the intersection and 900 block to traffic.
Roadway Closure – St. Ann Reconstruction
Entergy Gas and Entergy Electric have demobilized from their facility upgrades on St. Ann; crews will return on Tuesday, September 3. Residents and commuters should anticipate intermittent roadway closures while they complete their work. The City / SWBNO are in the process of designing the sewer, water and drainage work for this block. Once City / SWBNO work begins in the October timeframe, the block will be fenced off; specific scheduling details will follow in a future update.
Overall Project Sequence of Construction
Block |
Tentative
Schedule (Fence in place) |
*
Approximate Total Days Per Block (Including Sidewalks) |
500 (St. Louis – Toulouse) | 9/24/18 – 11/30/18 | 75 Days |
600 (Toulouse – St. Peter) | 12/03/18 – 1/27/19 | 75 Days |
700 (St. Peter – St. Ann) | 1/27/19 – 2/17/19, 5/20/19 – 7/8/2019 | 75 Days |
800/ 900 (St. Ann – Dumaine and 40ft into the 900 block) | 7/8/19 – 8/28/19 | 75 Days |
Total Days *Once the contractor moves the fence to the next block, sidewalks in the previous block will be worked on simultaneously | 250 Working Days Total (exclusive of weather / events days) |
AT&T Service Outage Reporting Process
To ensure service restoration and proper credit, AT&T residential customers
MUST report problems to 1-800-288-2020. Business customers MUST report
problems to 1-877-438-0041. After reporting problems to AT&T,
customers may also send e-mail to roadwork@nola.gov
to help expedite the process.
Garbage Corrals
Garbage must be placed in appropriate corrals at the end of each intersecting block between 4 a.m. to 8 a.m. and 4 p.m. to 8 p.m. Please refrain from leaving garbage cans on Bourbon St. as pedestrian access must be maintained. For more information, click here.
Questions about this project may be directed via e-mail to roadwork@nola.gov or to the RoadworkNOLA hotline 504.658.ROAD (7623).