The City is in the process of designing a full reconstruction project of Conti Street between Bourbon and Chartres streets. Ahead of construction, the city’s contractor will begin exploratory trenching in multiple locations per block to verify the location, depth and size of the utility lines underneath Conti Street. Exploratory trenching will take approximately three weeks to complete and includes the following:
The anticipated schedule is:
October 7 – October 16: 600 Block
October 17 (following completion of 600 Block) – October 28: 700 Block
Expect intermittent road and sidewalk closures, construction equipment, limited parking availability, elevated noise levels, dust, and continuous vibration monitoring.
Questions about this project may be directed to via e-mail to roadwork@nola.gov or to RoadworkNOLA hotline 504.658.ROAD (7623).